CONSTRUCTION SCHEDULE
FOR PHASE 1 WEST AND PHASE 1A
Road Closure and Detours: May 2025
Road Paving: November 2025
Road Open and Detours Removed: April 2026
Construction Completion: May 2026
PRELIMINARY SCHEDULE
FOR PHASE 1 EAST
Roadway Design: Ongoing; Complete Fall 2025
Archeology Investigation: Completed
Land Acquisition: Begin Spring 2025
Construction: Following Completion of Phase 1 West and Phase 1a
Anticipated Construction Duration: 12 Months